Whether it is a DNV surveyor walking our shop floor for an offshore hose reel frame, or a client QA engineer checking a batch of fuel tanks or rig steel, third-party inspection is part of normal life in our yard.
For project engineers ordering fabricated steel for the first time, an Inspection and Test Plan (ITP) can look intimidating on paper. In practice, it is just a structured series of common-sense checks done at the moments when fixing a problem is still easy.
1. Drawings, steel certificates and welder papers
The first visit often happens before a single spark flies. The inspector checks that the shop is working off the latest approved-for-construction drawings, verifies the mill test certificates against the stamps on the raw steel, and confirms the welding procedures and welder qualification cards match the processes being used.
2. Fit-up, welding and non-destructive testing
On critical joints, the inspector checks root gaps, bevel angles and alignment before full welding starts. Once welds are complete and cleaned, they inspect the weld profiles visually and review or witness the NDT — dye penetrant, magnetic particle, ultrasonic or X-ray, depending on the spec.
3. Tape-measure dimensional checks and functional tests
Before the unit moves to blasting, we walk around it with the inspector, the approved drawing and calibrated measuring tapes. Overall envelope, bolt-hole centres, diagonal squareness and lifting-point geometry all get recorded on the dimensional report. If the job calls for a hydrotest or a proof load test, it happens here too.
4. Blasting, coating thickness and final release
In the blast and paint area, the checks cover surface cleanliness, anchor profile, ambient temperature and humidity, and dry-film thickness (DFT) after each coat. Once the data plates are riveted on and the stencil markings are checked, the inspector signs the release note and the full manufacturing record book is handed over with the steel.