Most enquiries land in our inbox as a drawing and a target delivery date. That is plenty to start talking, though it is rarely enough to give you a firm price you can take to your project director. Two jobs built from the exact same drawing can end up weeks apart on schedule and miles apart on cost, depending on everything that sits around the steel itself.
If you want a solid quote back on the first reply instead of three days of back-and-forth emails, here is what helps us most.
Drawings — and make sure the revision is clear
Send over the general arrangement and fabrication drawings if you have them, with the latest revision marked. If you are still at the concept stage, or you only have a rough sketch or a photo of an existing unit, just tell us. We do design and shop detailing too, and it is much easier for everyone when we know from day one whether drawings are part of our scope.
If you are ordering a repeat of something you have bought before, let us know. Building a first-off prototype takes jigging, trial fit-up and extra checking; running off a repeat batch is a very different conversation.
Steel grade, certificates and quantity
Let us know the exact steel grade or standard you need, and whether you need full mill test certificates traced back to each heat number. Carbon steel, SS316 and SS316L behave completely differently on the shop floor — they use different consumables, different handling and separate work areas.
Quantity matters just as much, along with whether everything has to ship together or can leave in staged batches. Pricing sixty identical bunded fuel tanks works on completely different economics to pricing a single bespoke skid.
Third-party certification and inspection
More than anything else, this is the part that catches buyers out if it only comes up after the PO is signed. Tell us upfront whether a certifying body is involved — DNV 2.7-1 for offshore containers and lifting frames, API requirements on rig steel, or your own client ITP.
- Which third-party body or client inspector is reviewing the job.
- Which hold points need to be witnessed before we move to the next stage.
- What testing is expected: MPI, UT, radiography, load testing or dimensional reports.
- What needs to go into the final handover dossier.
Paint system, colour and markings
Include the coating specification if you have one, or simply tell us where the steel is going to live — coastal, offshore, buried, or inside a dry warehouse. Mention the final RAL shade and any stencilling, serial numbers or data plates. Because we handle sandblasting and airless painting in our own yard, we would always rather price it in from the start.
Where it is going and who lifts it
Ex-works pickup from our yard, delivery to your site, and full supply-and-install are three very different numbers. If you want our crew to erect the steel on site, tell us about access, crane space, night-shift rules or site safety permits so we can plan properly instead of guessing.